Construction Projects

Construction Project Upates for the week of 6/9/19

Street Overlay project – Adams Ave NW & 16th St SW: All the Catch basins, Manholes & Valves have been adjusted for the bituminous overlay. All curb & gutter and sidewalk has been removed. About half the C&G has been replaced so far.

19001 - 2019 Street and Utility Project

James Brothers Construction began work on Monday, June 10th on Holly Street from Linn Avenue to Butternut Avenue.

-Monday: Removed the asphalt service and began common exaction.

-Tuesday: Continued common excavation and place the aggregate base.

-Wednesday: Removed concrete walk, driveway pavement and curb & gutter. Also removed asphalt pavement on North Street from State Avenue to 533 feet west.

-Thursday: Began common excavation and back hauling aggregate base on North Street.

Street Maintenance (Crack seal & Seal coat): The Crack sealing is completed. The Seal-coating is completed in town, just one lot in the airport is remaining. The contractor will return in a few weeks to finish that.

CIPPS Sanitary Sewer project: The contractor has started pre-cleaning and televising the sewers.